Grid Load
72%
// ANSWER CONFIRMED
system verdict
Data centers have their own custom customer classifications in tariffs.
ROUND 03 VERDICT
Partial Myth
Precedent: Ohio PUC & AEP Settlement.
New Classification: Schedule Data Center Tariff (DCT).
Who: New loads or expansions > 25 MW.
Key Terms: Includes new collateral, exit fees, and ramp timelines. Minimum demand charge set at 85% of highest monthly billing.