Data centers in Texas will need to install equipment for remote disconnection.
ROUND 05 VERDICT
Fact
Mandate: Under Texas Senate Bill 6 (SB6), utilities must develop protocols to install remote disconnect equipment before interconnection during firm load shed (EEA3) events.
Trigger: EROCOT-defined thresholds for large load customers to deploy backup or curtail load during emergencies
Timeline: Implementation starting in 2026